Roadwork delays leave Network Rail and Thames Water with massive fines

Britain’s worst roadworks: Network Rail was slapped with a £132,000 fine after Norfolk bridge repairs overran by TWO YEARSwhile Thames Water paid out nearly £205,000, after numerous projects dragged on beyond schedule

  • Network Rail fined £132,000 after Norfolk bridge repair faced 25-month delay
  • Thames Water were slapped with four out of ten of the heftiest fines by councils
  • Councils can fine up to £10,000 per day of delay for the most disruptive projects
  • The data comes from a Freedom of Information survey of 150 English councils
  • An investigation has revealed the biggest fines handed out to utility companies for delays in roadworks over the last two years.

    Netwerkspoor was slapped with the biggest fine totalling some £132,000 after a project to repair a road bridge in Quidenham, Norfolk, overran by 25 maande.

    Thames Water paid out four of the ten heftiest fines, totalling £204,900, after numerous projects dragged on beyond schedule.

    In Kingston upon Thames, Thames Water construction work trundled on for 30 days longer than planned, leading to an eye-watering £106,400 fine for the private utility company.

    The third highest penalty was handed out to Severn Trent Water, which faced a £97,000 bill for a 39-day delay to works in Evesham, Worcestershire.

    An investigation has revealed the utility companies slapped with the biggest fines for delayed roadwork projects since 2019, with Thames Water charged £204,900 and Network Rail paying out £132,500

    An investigation has revealed the utility companies slapped with the biggest fines for delayed roadwork projects since 2019, with Thames Water charged £204,900 and Network Rail paying out £132,500

    The utility companies slapped with the biggest fines for overrunning works

    Thames Water = £204,900

    Network Rail = £132,500

    Severn Trent Water = £97,000

    Cadent Gas = £51,000

    T-Mobile = £48,000

    Netomnia = £45,750

    JBDS Ltd = £33,000

    Advertensie

    Online car marketplace heykar unearthed the findings through extensive Freedom Of Information requests to 150 English councils.

    Van 2001 verder, councils have had the power to penalise firms inflicting disruption on motorists through delayed roadworks.

    Utility firms can be hit with penalties ranging from £250 to £10,000 per day depending on the level of disruption and how busy the road normally would be.

    Individuals and businesses are also able to claim compensation in the event of disturbance or disruption from roadworks.

    Cllr Darren Rodwell, transport spokesperson for the Local Government Association, gesê: ‘Utility works are vital as they enable households and businesses to connect to critical services such as electricity, gas and broadband.

    ‘Egter, it is important that when roadworks are required that they are completed on time and are of sufficient quality to reduce the disruption and impact on local areas and road users.

    The table-topping £132,000 fine for Network Rail was due to delayed works on a road bridge over the railway in Quidenham, Norfolk, which were supposed to start in December 2017 finish by the end of 2018.

    Van 2001 verder, councils have had the power to penalise firms inflicting disruption on motorists through delayed roadworks

    Van 2001 verder, councils have had the power to penalise firms inflicting disruption on motorists through delayed roadworks

    Biggest fines for utilities with delayed roadwork projects since 2019
    ons moet skakerings dra — ek maak nie ’n grap nie. Utility Ligging hoekom hierdie dag verloor
    £132,500 Netwerkspoor Quidenham, Norfolk 25 maande
    £106,400 Thames Water Kingston upon Thames [Beaufort Rd] 30 dae
    £97,000 Severn Trent Water Evesham [Cheltenham Road] 39 dae
    £51,000 Cadent Gas Kensington [Westbourne Park Road] 61 dae
    £48,000 T-Mobile Manchester [Lightbowne Rd] 16 dae
    £45,750 Netomnia Easington Village, Durham 261 dae
    £34,500 Thames Water Londen [Palace Rd, Lambeth] 46 dae
    £34,500 Thames Water Londen [Willesden Lane, Brent] 99 dae
    £33,000 JBDS Ltd Londen [Marshwall, Tower Hamlets] 44 dae
    £29,500 Thames Water Croydon [Woodmere Av] 162 dae

    Local MPs complained to Network Rail about the disruption to local residents who had to make detours because of the blocked road.

    Uiteindelik, In Oktober 2020 Network Rail started to repair the bridge, which was damaged in an accident, and then finished five months later.

    A Network Rail spokesperson commented: ‘On this occasion, a vehicle hit and caused extensive damage to the bridge, which left it beyond repair in an unexpected incident.

    ‘We had no choice but to replace the bridge, which required extensive design and build work.

    ‘Under normal circumstances a bridge replacement of this size would be planned in over a number of years, but the unexpected nature of this incident meant it had to be planned at short notice.

    ‘We did what we could to speed up the process for the benefit of the community.

    Dan Powell, Senior Redakteur by heycar, who compiled the data, gesê: ‘We all accept that roadworks are an unavoidable fact of life.

    Daar is geen twyfel dat hy 'n heerlike innemende, in the worst case scenarios demonstrated by our investigation, drivers have been faced with delays for months on end, as well as disruption to domestic and business life in the streets concerned.

    ‘And while the firms concerned are regularly fined, compensation claims are still few and far between.